PERIOD : oct/1975 to mar/1977

Job Title: Field Project Engineer,  reporting to Projetc Manager

Coordinate field engineering construction and installation project activities of São Paulo Plant expansion, which consist of:

Installation of new glass furnace capable to produce 200 Tons/day substitute existing 40 Tons/day glass furnace

Installation new raw material storage and preparation facilities capable to feed 4 furnace with capacity of  200Tons/day 

Expanding existing final products warehouse

Expanding and upgrading existing utilities (refrigerating water and compressed air systems)

 

 